GUIDE / SITE PLAN CLOSE-OUT

Hamilton Landscape Securities: How Release Works on Site Plan Projects

Newly installed shrubs, staked young trees, mulch beds and fresh sod along a walkway beside a low-rise commercial building
QUICK ANSWER
  • In Hamilton, are held until the City is satisfied the approved landscape works are built and established. Your site plan agreement sets the timing.
  • Release timing and conditions, such as inspections, sign-off and any partial reductions, are set by your site plan agreement. Confirm them with the City.
  • Build exactly what the approved plan shows, and get every substitution approved in writing first.
  • Dead plants and open deficiencies are common reasons money stays held.

This page is for general planning only. It is not legal or engineering advice. Check current rules with the regulation, your municipality and your consultants.

01 —

What landscape securities are and why they're held

When a Hamilton site plan is approved, the landscape works shown on the approved landscape plan become part of the site plan agreement. The City holds landscape securities to make sure those works get built.

The City holds landscape securities until it's satisfied the approved landscape works are built and the planting has established. Release timing and conditions, such as inspections, sign-off and any partial reductions, are set by your site plan agreement. Confirm them with the City.

For an owner or developer, the goal is simple: build what was approved, document it and close out cleanly.

02 —

Who prepares the plans

Grading and landscape plans for site plan approval usually need a stamp from an architect, engineer or landscape architect. Minor projects can be exempt. In Hamilton, landscape plans are prepared by an Ontario Association of Landscape Architects (OALA) landscape architect.

The landscape contractor builds to those stamped drawings. Changes go back through the consultant rather than being decided in the field.

03 —

How release works

The City holds landscape securities until it's satisfied the approved landscape works are built and the planting has established. Release timing and conditions, such as inspections, sign-off and any partial reductions, are set by your site plan agreement. Confirm them with the City.

  • Hamilton’s standard landscape notes require landscaping to be installed "prior to the end of the first growing season following the occupancy".
  • On Hamilton-reviewed plans, contractors give a minimum one-year warranty from acceptance.
  • 25% of a tree protection deposit is held for a two-year maintenance period.

Securities timeline

For owners and developers closing out a Hamilton site plan. Shows the steps to confirm in your agreement.

  1. 01Install
  2. 02Inspection & sign-off
  3. 03First growing season
  4. 04Release (per your agreement)
Release depends on your agreement and sign-off

Close-out checklist

  • As-planted matches plan
  • Substitutions approved in writing
  • Plants alive after the first growing season
  • Deficiency list cleared
How we calculated this

This is a sequence, not a date calculator. The City holds landscape securities until it's satisfied the approved landscape works are built and the planting has established. Release timing and conditions, such as inspections, sign-off and any partial reductions, are set by your site plan agreement. Confirm them with the City.

Next: review your agreement with the City and consultant.

04 —

Common reasons securities stay held

Most delays trace back to differences between what was approved and what is on the ground, or to paperwork that was never completed.

  • Off-plan planting — locations, quantities or layouts that don't match the approved plan
  • Unapproved substitutions of species, sizes or materials
  • Dead or missing plant material after the first season
  • Incomplete deficiencies from the consultant's inspection
  • Missing sign-off required by the agreement
05 —

Close-out checklist

Before asking for a reduction or release, walk the site against the approved plan.

  • As-planted layout matches the approved landscape plan
  • Every substitution approved in writing before installation
  • Plant material alive and healthy after the first growing season; replacements installed
  • Consultant's deficiency list cleared
  • Sign-off required by your agreement
06 —

How a landscape contractor fits in

We build the approved plan as drawn. We flag substitutions before ordering, record what was installed and clear deficiencies for inspection and sign-off. The design and agreement terms stay with the consultant, the owner and the City.

FAQ —

Frequently asked questions

When are Hamilton landscape securities released?

The City holds landscape securities until it's satisfied the approved landscape works are built and the planting has established. Release timing and conditions, such as inspections, sign-off and any partial reductions, are set by your site plan agreement. Confirm them with the City.

Who certifies the landscape work?

It depends on your agreement. Your site plan agreement sets who inspects and signs off on the landscape work. That often involves the project's landscape architect. Confirm with the City and your consultant.

Can landscape securities be reduced partway through?

It depends on your agreement. Release conditions are set by your site plan agreement. Confirm what's possible with the City and your consultant.

Do plant substitutions need approval?

Yes. Get every substitution approved in writing through your consultant before planting. Unapproved swaps are a common reason money stays held.

RELATED —

Related

Request a bid

Send drawings, site details and a tender reference if you have one. Or call (647) 459-7775.

What happens next

  1. We review your drawings and scope.
  2. We call or email to confirm details and questions.
  3. You get a priced scope.